How Do I Apply?
Submit the accomplished form at CEDC office together with the required documents based on the following type of application:
- Accomplished Application Form.
- Company Profile (Business Information, Brief History, Mission/Vision and Management).
-
Electrical Plans Certified by a Licensed Professional Electrical Engineer (1 set).
a) Location Plan
b) Load Schedule, Computations and One Line Diagram - Copy of Site Development Plan."
- Copy of Lease Agreement with Clark Development Corporation (CDC) or Sub-Lease Agreement (with attached accomplished Undertaking).
- Copy of Certificate of Registration and Tax Exemption (CORTE) from CDC.
- Originial copy of notarized Board Resolution authorizing person/s to sign, negotiate and transact with CEDC on behalf of the Corporation.
- Copy of valid IDs of Corporate Secretary or Authorized Person/s (for Corporate Accounts).
- Tax Identification Number (TIN).
- Certificate of Electrical Inspection (CEI) from CDC.
- Contract of Service.
- Data Privacy Act (DPA) Consent Form.
- Bill/Security Deposit.
Note: Items no. 2, 6, 7, 8 and 9 are only applicable to corporate accounts.
- Accomplished Application Form.
- Company Profile (Business Information, Brief History, Mission/Vision and Management).
-
Electrical Plans Certified by a Licensed Professional Electrical Engineer (1 set).
a) Location Plan
b) Load Schedule, Computations and One Line Diagram
c) For electric motors larger than 15 HP, they should have a motor control diagram. These motors should have reduced voltage starting device.
d) For Indoor or Outdoor Substation- Equipment Layout & Installation Drawings
- Specification of Major Electrical Equipment & Devices Switching Structure Drawings.
- Grounding System Drawings
- Transformer test reports (Manufacturer and On-site, Hi-pot test for XLPE power cable, Protection Relay Settings, Transformer Bushing Capacitance test reports and other pertinent technical data as maybe required.
- Vault Room Plan/Transformer Pad Plan for application involving installation of CEDC Pad mounted Transformer and Primary Metering Vault.
- If development is 7MVA or above, negotiation for substation lot wil be required.
- Copy of Site Development Plan.
- Copy of Lease Agreement with Clark Development Corporation (CDC) or Sub-Lease Agreement (with attached accomplished Undertaking).
- Copy of Certificate of Registration and Tax Exemption (CORTE) from CDC.
- Originial copy of notarized Board Resolution authorizing person/s to sign, negotiate and transact with CEDC on behalf of the Corporation.
- Copy of valid IDs of Corporate Secretary or Authorized Person/s (for Corporate Accounts).
- Tax Identification Number (TIN).
- Certificate of Electrical Inspection (CEI) from CDC.
- Contract of Service.
- Data Privacy Act (DPA) Consent Form.
- Bill/Security Deposit.
- Accomplished Application Form.
- Company Profile (Business Information, Brief History, Mission/Vision and Management).
- Location Map.
- Electrical Plans consisting of wiring layout, vicinity plan, load schedule, computations and one-line-diagra, (certified by a licensed Professional Electrical Engineer). For electric motors larger than 15 HP should have a motor control diagram, these motors should have reduced voltage starting device.
- Copy of Lease Agreement with Clark Development Corporation (CDC) or Sub-Lease Agreement or Copy of Contract with Lessee (for Contractors applying for the temporary power).
- Copy of Certificate of Registration and Tax Exemption (CORTE) from CDC.
- Original copy of notarized Board Resolution as to who is/are the Authorized Person/s to transact, give instructions, gsign all documents and contracts for & in behalf of the Corporation with regard to its transactions with CEDC (for Corporate Accounts).
- Copy of Valid IDs of Corporate Secretary or Authorized Person/s (for Corporate Accounts).
- Tax Identification Number (for E-VAT locators).
- Certificate of Electrical Inspection (CEI) from CDC.
- Agreement for the Sale of Electric Energy
- Bill Deposit and Installation/Removal charge.
Non-compliance with the above-listed requirements will delay the processing of application.
- After completion and evaluation of all the requirements, a base meter will be issued by CEDC and to be installed by the customer’s qualified contractor/electrician (for Non-CT rated connections).
- Once the base meter is installed, please inform Clark Electric and submit a photo of the installed base meter and service pedestal.
- Our representative will then conduct a survey to ensure that the installed base meter and service pedestal is compliant with the technical requirements of Clark Electric.
- You will be contacted by Clark Electric regarding the result of the survey. If rework is needed, please make sure that the recommendation given are followed.
-
Upon verification on the field, our Customer Service Engineer will compute for the bill deposit.
- The bill deposit is equivalent to the computed/estimated one-month billing.
- CEDC shall pay interest on bill deposits equivalent to the prevailing interest rate for savings deposit as approved by the Bangko Sentral ng Pilipinas (BSP)
- Bill Deposit is refundable upon termination of contract.
Note: Facility installation and removal charge will be imposed for temporary power application (non-refundable).
- Visit CEDC office to pay for the bill deposit and sign the contract of service (Residential application) and Agreement for the Sale of Electric Energy (Non-Residential/Temporary application).
- Our representative will install your electric meter on the scheduled date of energization.